Title:
|
A resolution awarding a contract to R. L. Alia Company, in the amount of $518,516.50, excluding sales tax, plus a 15 percent contingency, for a total of $596,293.98, budgeted from the Wastewater Fund, for the removal and construction of approximately 2,200 linear feet of underground wastewater mains, and roadway surface restoration in various locations within the City - Specification No. ES16-0281F.
[Geoffrey M. Smyth, P.E., Science and Engineering Division Manager;
Michael P. Slevin III, P.E., Director, Environmental Services]
|