Title: A resolution awarding a contract to R.L. Alia Company, in the amount of $1,084,473.50, plus applicable taxes, plus a 15 percent contingency, budgeted from various departmental funds, for wastewater and stormwater sewer improvements along South Cushman Avenue, South 35th Street, and South Wright Avenue, for a projected contract total of $1,247,144.52 - Specification No. ES23-0055F. [Jordan Ennis, P.E., Science and Engineering Civil Engineer; Michael P. Slevin III, Director, Environmental Services; Josh Diekmann, Interim Director, Public Works]
Attachments: 1. Resolution No. 41254, 2. Contract and Award Memorandum

Title

A resolution awarding a contract to R.L. Alia Company, in the amount

of $1,084,473.50, plus applicable taxes, plus a 15 percent contingency,

budgeted from various departmental funds, for wastewater and stormwater

sewer improvements along South Cushman Avenue, South 35th Street,

and South Wright Avenue, for a projected contract total of $1,247,144.52 -

Specification No. ES23-0055F.

[Jordan Ennis, P.E., Science and Engineering Civil Engineer;

Michael P. Slevin III, Director, Environmental Services;

Josh Diekmann, Interim Director, Public Works]