File #: RES41191    Version: 1 Name: Purchase Resolution – Central Treatment Plant Secondary Clarifier No. 5 Restoration Project
Type: Resolution Status: Adopted
File created: 4/27/2023 In control: City Council
On agenda: 5/9/2023 Final action: 5/9/2023
Title: A resolution awarding a contract to Rognlin's, Inc., in the amount of $1,436,500, plus applicable taxes, plus a 20 percent contingency, budgeted from the Wastewater Fund, for construction of the Central Treatment Plant Secondary Clarifier No. 5 Restoration Project, for a projected contract total of $1,723,800 - Specification No. ES23-0026F. [Lance Bunch, P.E., Project Manager; Michael P. Slevin III, P.E., Director, Environmental Services]
Attachments: 1. Resolution No. 41191, 2. Contract and Award Memorandum

Title

A resolution awarding a contract to Rognlin’s, Inc., in the amount of $1,436,500, plus applicable taxes, plus a 20 percent contingency, budgeted from the Wastewater Fund, for construction of the Central Treatment Plant Secondary Clarifier No. 5 Restoration Project, for a projected contract total of $1,723,800 - Specification No. ES23-0026F.

[Lance Bunch, P.E., Project Manager; Michael P. Slevin III, P.E., Director,

Environmental Services]